The Abbey Church apartments

This building will be completed in spring and summer 2012. More will be added here as information becomes available.
The swimming pool is part of this last phase in the development will be last to be completed and it is estimated that it will be completed early in 2012.
Following a visit in January 2012 we can say that the pool and spa is complete as you can see in our Abbey Church gallery. many of the apartments are complete and are in the process of being furnished ready for holiday letting, but there are technical problems with the pool so filling and draining to treat leaks etc is in progress. It is likely that the pool will be open in early March, now 2 years later than first estimates! From what we saw, a couple of months finishing apartments and landscaping grounds should see the work finished totally. However we do not garantee this 100% as this is in the hands of the developers who will not commit to a date. We are hopeful though for early March completion.
|